Skip survey header
Practical Law - A Thomson Reuters Legal Solution

Q&A: CPD: Construction Act webinar September 2011

1. If a main contractor enters into its main contract with an Employer, for construction operations in England, dated 1 September 2011… *This question is required.
2. What are the two key payment notices under the Construction Act 1996 (as amended)? *This question is required.
3. Who can serve the employer's formal notice (as the paying party under a construction contract), setting out how much the employer intends to pay? *This question is required.
4. You are a professional consultant. Your professional appointment (a construction contract) requires your client to notify you how much it intends to pay you each month, based on an agreed schedule of payments in your professional appointment. You haven't received any notice from your client this month, and you want to be paid. You should… *This question is required.
5. A main contractor wants to impose a contra-charge on a sub-contractor on a project carried out in England. The sub-contract is a construction contract dated 1 November 2011 and the sub-contract permits the main contractor to levy the contra-charge. The contra-charge would mean that the next monthly payment from the main contractor to the sub-contractor will be zero. The main contractor: *This question is required.
6. If a commercial property developer has a cash flow problem and can't pay its main contractor on time one month, assuming the main contract is dated on or after 1 October 2011 for construction operations in England or Wales, which one of these options gives the best description of the main contractor's right of suspension? The main contractor has a statutory right to: *This question is required.
7. An architect and a structural engineer agree that the architect will pay the engineer £5,000 (plus VAT) to advise the architect on a structural element of the architect's detailed designs for a property developer. They reach this agreement on 5 November 2011. They reach this agreement:
  • Scenario one: On the phone.
  • Scenario two: On the phone, which they then confirm by exchange of emails.
  • Scenario three: On the phone, as an addition to an existing written agreement between them (dated 5  October 2011) for the engineer to design the drainage systems for the same development.
  • Scenario four: In an exchange of letters, as an addition to an existing agreement between them (dated 5 October 2011) for the engineer to design the drainage systems for the same development.
Which of these scenarios (at least potentially) describes a construction contract or construction contracts? *This question is required.
8. A construction contract dated 1 December 2011, for construction operations in Wales, does not require an adjudicator to reach his decision within 28 days of the referral (or such longer period as is agreed by the parties after the dispute has been referred). Because of this omission: *This question is required.
9. An adjudicator has issued his decision, relating to a construction contract entered into after 1 October 2011, for construction operations in England. The relevant amended Scheme for Construction Contracts applied to the adjudication. The party ordered to make payment under the decision spots a simple arithmetic error in the decision, meaning it would have to pay more. Which of these statements best summarises the paying party's rights: *This question is required.
10. The amendments to the Construction Act 1996 include a ban on so-called Tolent clauses. Given this statutory ban: *This question is required.